Our team
We congratulated our sales representative Matt on running the Hartford Marathon after months of training.

A closer look at our crew, equipment and infrastructure work.
Our team
We congratulated our sales representative Matt on running the Hartford Marathon after months of training.
Company event
Gino and Matt will represent us at the Boston Buildings Engineering & Facility Maintenance Show on October 15. Stop by Booth #325 to meet our team and ask questions.
Our team
We celebrated our COO and owner Travis’s birthday by sharing a few moments with our team, around our company vehicles and out in the field.
Our team
Our sales representatives took part in the Manafort Brothers charity golf tournament and caught up with industry colleagues.
Coatings and linings
Our coating and lining work at a transformer station progressed from surface preparation and masking around existing equipment to the finished coating.
Waterproofing
We completed waterproofing work on an aeration tank wall. These photos show the wall and the crack repair details.
Infrastructure restoration
Our crew restored a red brick invert at the base of a manhole. The invert forms the channel that directs wastewater through the structure.
Pipe lining
After installing a cured-in-place pipe liner, we use robotic cutting equipment to reopen the service connections covered by the liner. These inspection images show a lateral reinstatement inside the pipe.
Coatings and linings
One of our crew members photographed this manhole from the inside after we completed invert resurfacing and applied protective coatings. The view looks up toward the access opening.
Coatings and linings
We prepared a heater tank, reactor tank and reflux condenser by media blasting, then applied a two-coat protective coating system with a glass flake additive. These photos document the coating work and inspection details.
Water and wastewater
Our team inspected a fresh water suppression tank. The photos show the tank and its access opening during the inspection.
Chemical grouting
We used grout injection to seal leaks at a catch basin without excavating the structure. The photo shows injection equipment set up at the pavement around the basin.
Our team
We brought the team together for a new Savy & Sons group photo. These are the people behind our projects and service calls.
Camera inspection
We inspected approximately 350 to 400 feet of 8-inch sanitary sewer pipe, from the manhole to the city sewer main. This photo shows the inspection equipment inside the manhole.
Slab stabilization
Our crew used stem injection beneath a settled slab to restore support. The photo shows the injection setup across the floor before the space was finished.
Pipe lining video
We rehabilitated 52 feet of 15-inch pipe using cured-in-place technology through existing catch basins.
Pipe lining video
We shared another look at our crew carrying out a cured-in-place pipe installation. The video shows the teamwork involved in restoring underground infrastructure.